Open for a Month, San Francisco's Transit Terminal Shut Down Due to Cracked Beams

The $2.2 billion Salesforce Transit Center, which opened to much celebration on Aug. 11, closed down abruptly Sept. 25 after workers found a cracked steel beam. A second cracked beam was later found. Work began Sunday to shore up the structure.

3 minute read

October 1, 2018, 2:00 PM PDT

By Irvin Dawid


San Francisco, California

Chris W Anderson / Shutterstock

"The cracked beam was spotted Tuesday morning by workers installing ceiling panels on the center’s third-floor bus platform, and concern over its potential failure prompted city officials to close the terminal and some streets at 4:30 p.m," report Matier & Ross for the Chronicle on Sept. 28.

They shunted rush-hour commuters to the nearby Temporary Transbay Terminal, which had been used during the center’s construction.

During an overnight inspection of the center, which opened on Aug. 11, a second crack was discovered, though smaller than "[t]he initial tear [that] runs about 2½ feet long and 4 inches deep through the bottom of a 60-foot-long beam that supports both the center’s celebrated rooftop park above and a bus deck below," reported the Chronicle's Kurtis Alexander and Evan Sernoffsky on Sept. 27.

Representatives of the Transbay Joint Powers Authority, which built and operates the transit center, said Wednesday they didn’t know the causes of the cracks, but they remained concerned about the potential for the beams to fail. Fremont Street, which passes under the center, also is scheduled to stay closed through Oct. 5.

The Chronicle's urban design critic, John King, delves into the structural engineering aspects of the three-block, 1,500-foot building that "twice span major roadways."

Those spans are supported by just four massive beams. Two of them have cracked.

What makes the situation so worrisome is that the cracked girders are the primary means of support for the transit center as it spans Fremont. The only things below the bus deck are sidewalks and asphalt.

King interviewed many structural engineers for the story. 

“You’ve got a bus deck hanging from a column that in turn is held up by two cracked beams,” said Joe Maffei, founder of San Francisco’s Maffei Structural Engineering...“I think we are lucky that there was not a collapse.”

While it is not known what caused the cracking of the steel beams which were fabricated by Herrick Corp. in Stockton, Calif., King offers one possiblity:

The most troubling scenario is that the design by Thornton Tomassetti structural engineers and Pelli Clark Pelli Architects didn’t adequately account for the twin pressures of a bus deck and rooftop.

"Hydraulic jacks and newly fabricated steel beams arrived Sunday morning ... where they’ll be used to shore up the spot over Fremont Street where cracks were discovered," reports Michael Cabanatuan on Sept. 30.

By midnight Sunday, Mark Zabaneh, director for the Transbay Joint Powers Authority, said the first of three phases of shoring up the transit center should be completed. It’s not yet clear how long the whole process will take, but by Monday or Tuesday, he said, authorities should have a better idea of when they can partially open Fremont Street.

Once crews install the temporary bracing, it will relieve weight from the damaged girders and allow extensive testing to help determine the cause of the cracking. It could take a week or longer to get results of those tests, he said.

Matier and Ross note the proximity of the transit center to two other engineering failures:

  • The center sits next to the troubled Millennium Tower, which has sunk 18 inches since it opened in 2009. 
  • The cracked beam is also reminiscent of the cracked bolts that plagued the eastern span of the Bay Bridge.

Related in Planetizen

Saturday, September 29, 2018 in San Francisco Chronicle

portrait of professional woman

I love the variety of courses, many practical, and all richly illustrated. They have inspired many ideas that I've applied in practice, and in my own teaching. Mary G., Urban Planner

I love the variety of courses, many practical, and all richly illustrated. They have inspired many ideas that I've applied in practice, and in my own teaching.

Mary G., Urban Planner

Get top-rated, practical training

Red 1972 Ford Pinto with black racing stripes on display with man sitting in driver's seat.

Analysis: Cybertruck Fatality Rate Far Exceeds That of Ford Pinto

The Tesla Cybertruck was recalled seven times last year.

July 2, 2025 - Mother Jones

Close-up of park ranger in green jacket and khaki hat looking out at Bryce Canyon National Park red rock formations.

National Parks Layoffs Will Cause Communities to Lose Billions

Thousands of essential park workers were laid off this week, just before the busy spring break season.

February 18, 2025 - National Parks Traveler

Paved walking path next to canal in The Woodlands, Texas with office buildings in background.

Retro-silient?: America’s First “Eco-burb,” The Woodlands Turns 50

A master-planned community north of Houston offers lessons on green infrastructure and resilient design, but falls short of its founder’s lofty affordability and walkability goals.

February 19, 2025 - Greg Flisram

Screenshot of shade map of Buffalo, New York with legend.

Test News Post 1

This is a summary

0 seconds ago - 2TheAdvocate.com

Red 1972 Ford Pinto with black racing stripes on display with man sitting in driver's seat.

Analysis: Cybertruck Fatality Rate Far Exceeds That of Ford Pinto

The Tesla Cybertruck was recalled seven times last year.

18 minutes ago - Mother Jones

test alt text

Test News Headline 46

Test for the image on the front page.

March 5 - Cleantech blog