Delays, Cost Overruns Shorten L.A. Metro's Gold Line Extension

The first light rail line to extend beyond Los Angeles County into the Inland Empire has had to rethink its construction schedule in response to skyrocketing costs.

1 minute read

November 15, 2018, 11:00 AM PST

By James Brasuell @CasualBrasuell


Foothill Gold Line Light Rail Extension

Foothill Gold Line Construction Authority via Metro / Foothill Gold Line Light Rail Extension

"Citing tariffs on imported steel, tighter immigration policies and rising wages, the Gold Line Construction Authority board Tuesday voted to build only half the Glendora-to-Montclair extension, saying runaway construction costs could prevent building out to Montclair," reports Steve Scauzillo.

"By a 5-0 unanimous vote, the board authorized the surprise staff recommendation that the 12.3-mile extension needs to be built in two phases due to costs rising 38 percent, from $1.5 billion to $2.1 billion," adds Scauzillo.

The new phased approach to construction means that the first eight miles of the extension, with stations in Glendora, San Dimas, and La Verne, will be complete in 2024, two years earlier than planned.

Scauzillo provides a lot more detail on the project and the Gold Line Construction Authority's reaction to the challenges facing the project. Steven Sharp provides additional analysis in a separate article.

Tuesday, November 13, 2018 in Daily Bulletin

portrait of professional woman

I love the variety of courses, many practical, and all richly illustrated. They have inspired many ideas that I've applied in practice, and in my own teaching. Mary G., Urban Planner

I love the variety of courses, many practical, and all richly illustrated. They have inspired many ideas that I've applied in practice, and in my own teaching.

Mary G., Urban Planner

Get top-rated, practical training

Red 1972 Ford Pinto with black racing stripes on display with man sitting in driver's seat.

Analysis: Cybertruck Fatality Rate Far Exceeds That of Ford Pinto

The Tesla Cybertruck was recalled seven times last year.

July 2, 2025 - Mother Jones

Close-up of park ranger in green jacket and khaki hat looking out at Bryce Canyon National Park red rock formations.

National Parks Layoffs Will Cause Communities to Lose Billions

Thousands of essential park workers were laid off this week, just before the busy spring break season.

February 18, 2025 - National Parks Traveler

Paved walking path next to canal in The Woodlands, Texas with office buildings in background.

Retro-silient?: America’s First “Eco-burb,” The Woodlands Turns 50

A master-planned community north of Houston offers lessons on green infrastructure and resilient design, but falls short of its founder’s lofty affordability and walkability goals.

February 19, 2025 - Greg Flisram

Screenshot of shade map of Buffalo, New York with legend.

Test News Post 1

This is a summary

0 seconds ago - 2TheAdvocate.com

Red 1972 Ford Pinto with black racing stripes on display with man sitting in driver's seat.

Analysis: Cybertruck Fatality Rate Far Exceeds That of Ford Pinto

The Tesla Cybertruck was recalled seven times last year.

18 minutes ago - Mother Jones

test alt text

Test News Headline 46

Test for the image on the front page.

March 5 - Cleantech blog