Project documents acquired by The Washington Post reveal numerous unresolved problems with construction on the Purple Line.

"The opening of Maryland’s Purple Line is at least a year behind schedule, and delays have added at least $215 million to the light-rail line’s cost," reports Katherine Shaver.
Now the Purple Line is expected to open in February 2023, "almost a year behind the March 2022 opening date in the project’s contract and four months behind the October 2022 date that Maryland transit officials insist is still possible," according to Shaver.
Apparently there is still dispute over the potential opening data. State transportation officials are pushing Purple Line Transit Partners (PLTP), "a team of companies building the 16-mile line and helping to finance its construction," to accelerate work to stick closer to the original schedule. Meanwhile, contractors have also proposed a much later opening date of June 2024.
There are $5.6 billion reasons for PLTP and the state to figure out a way to get on the same page. "PLTP and the state signed a $5.6 billion contract — one of the largest ever in Maryland — for the private consortium to design and build the line and then operate and maintain it for 30 years. PLTP also is helping to finance the line’s $2.4 billion construction," according to Shaver.
FULL STORY: Purple Line will open a year late and delays will cost at least $215 million, contractor says

Analysis: Cybertruck Fatality Rate Far Exceeds That of Ford Pinto
The Tesla Cybertruck was recalled seven times last year.

National Parks Layoffs Will Cause Communities to Lose Billions
Thousands of essential park workers were laid off this week, just before the busy spring break season.

Retro-silient?: America’s First “Eco-burb,” The Woodlands Turns 50
A master-planned community north of Houston offers lessons on green infrastructure and resilient design, but falls short of its founder’s lofty affordability and walkability goals.

Test News Post 1
This is a summary

Analysis: Cybertruck Fatality Rate Far Exceeds That of Ford Pinto
The Tesla Cybertruck was recalled seven times last year.

Test News Headline 46
Test for the image on the front page.
Urban Design for Planners 1: Software Tools
This six-course series explores essential urban design concepts using open source software and equips planners with the tools they need to participate fully in the urban design process.
Planning for Universal Design
Learn the tools for implementing Universal Design in planning regulations.
EMC Planning Group, Inc.
Planetizen
Planetizen
Mpact (formerly Rail~Volution)
Great Falls Development Authority, Inc.
HUDs Office of Policy Development and Research
NYU Wagner Graduate School of Public Service