Cost Overruns and Delays Causing Drama on Maryland's Purple Line

Project documents acquired by The Washington Post reveal numerous unresolved problems with construction on the Purple Line.

1 minute read

January 11, 2019, 8:00 AM PST

By James Brasuell @CasualBrasuell


Maryland Transit Administration

Maryland Department of Transportation / Purple Line Alignment

"The opening of Maryland’s Purple Line is at least a year behind schedule, and delays have added at least $215 million to the light-rail line’s cost," reports Katherine Shaver.

Now the Purple Line is expected to open in February 2023, "almost a year behind the March 2022 opening date in the project’s contract and four months behind the October 2022 date that Maryland transit officials insist is still possible," according to Shaver.

Apparently there is still dispute over the potential opening data. State transportation officials are pushing Purple Line Transit Partners (PLTP), "a team of companies building the 16-mile line and helping to finance its construction," to accelerate work to stick closer to the original schedule. Meanwhile, contractors have also proposed a much later opening date of June 2024.

There are $5.6 billion reasons for PLTP and the state to figure out a way to get on the same page. "PLTP and the state signed a $5.6 billion contract — one of the largest ever in Maryland — for the private consortium to design and build the line and then operate and maintain it for 30 years. PLTP also is helping to finance the line’s $2.4 billion construction," according to Shaver.

Thursday, January 10, 2019 in The Washington Post

portrait of professional woman

I love the variety of courses, many practical, and all richly illustrated. They have inspired many ideas that I've applied in practice, and in my own teaching. Mary G., Urban Planner

I love the variety of courses, many practical, and all richly illustrated. They have inspired many ideas that I've applied in practice, and in my own teaching.

Mary G., Urban Planner

Get top-rated, practical training

Red 1972 Ford Pinto with black racing stripes on display with man sitting in driver's seat.

Analysis: Cybertruck Fatality Rate Far Exceeds That of Ford Pinto

The Tesla Cybertruck was recalled seven times last year.

2 hours ago - Mother Jones

Close-up of park ranger in green jacket and khaki hat looking out at Bryce Canyon National Park red rock formations.

National Parks Layoffs Will Cause Communities to Lose Billions

Thousands of essential park workers were laid off this week, just before the busy spring break season.

February 18, 2025 - National Parks Traveler

Paved walking path next to canal in The Woodlands, Texas with office buildings in background.

Retro-silient?: America’s First “Eco-burb,” The Woodlands Turns 50

A master-planned community north of Houston offers lessons on green infrastructure and resilient design, but falls short of its founder’s lofty affordability and walkability goals.

February 19, 2025 - Greg Flisram

Screenshot of shade map of Buffalo, New York with legend.

Test News Post 1

This is a summary

0 seconds ago - 2TheAdvocate.com

Red 1972 Ford Pinto with black racing stripes on display with man sitting in driver's seat.

Analysis: Cybertruck Fatality Rate Far Exceeds That of Ford Pinto

The Tesla Cybertruck was recalled seven times last year.

18 minutes ago - Mother Jones

test alt text

Test News Headline 46

Test for the image on the front page.

March 5 - Cleantech blog