A perhaps surprising measure of success has been achieved by the New York Metropolitan Transportation Authority.

"The MTA’s dreaded repairs to the L train’s East River tunnel were completed ahead of schedule, despite the coronavirus pandemic," reports Caroline Spivack.
The news came in an announcement by Gov. Andrew Cuomo on Sunday, April 26. The governor caused a stir in back in January 2019 with last minute changes for plans to shut down the L Train between Brooklyn and Manhattan to repairs fix damages caused by Superstorm Sandy. Spivack explains more about what the project has accomplished in wrapping up repair work ahead of schedule.
Work on the Hurricane Sandy-damaged Canarsie Tunnel was initially scheduled to wrap up in July 2020 at the earliest to the tune of $500 million, but MTA officials said last year that the rehab was going so well that they expected to wrap up work by April. Transit officials say the project is being finished for nearly $100 million less than the original price tag.
The news about a transit project outperforming expectations in New York City is a notable change from years of delays and record costs. The worst effects of the once-dreaded L Train closure also seem to have been avoided.
FULL STORY: L train tunnel repairs completed ahead of schedule

National Parks Layoffs Will Cause Communities to Lose Billions
Thousands of essential park workers were laid off this week, just before the busy spring break season.

Retro-silient?: America’s First “Eco-burb,” The Woodlands Turns 50
A master-planned community north of Houston offers lessons on green infrastructure and resilient design, but falls short of its founder’s lofty affordability and walkability goals.

Delivering for America Plan Will Downgrade Mail Service in at Least 49.5 Percent of Zip Codes
Republican and Democrat lawmakers criticize the plan for its disproportionate negative impact on rural communities.

Test News Post 1
This is a summary

Test News Headline 46
Test for the image on the front page.

Balancing Bombs and Butterflies: How the National Guard Protects a Rare Species
The National Guard at Fort Indiantown Gap uses GIS technology and land management strategies to balance military training with conservation efforts, ensuring the survival of the rare eastern regal fritillary butterfly.
Urban Design for Planners 1: Software Tools
This six-course series explores essential urban design concepts using open source software and equips planners with the tools they need to participate fully in the urban design process.
Planning for Universal Design
Learn the tools for implementing Universal Design in planning regulations.
EMC Planning Group, Inc.
Planetizen
Planetizen
Mpact (formerly Rail~Volution)
Great Falls Development Authority, Inc.
HUDs Office of Policy Development and Research
NYU Wagner Graduate School of Public Service