An innovative tunneling technique, commonly used in Europe, is catching on here in the United States.

The Brightline high-speed rail extension from West Palm Beach, Florida, to Orlando International Airport (OIA) will use an innovative box-jack system to accelerate the construction timeline of a tunnel from one year to two weeks.
"This is the first time the box-jack system will be used for a train project outside of the Northeast United States," reports Kim Slowey. The construction technique has been implemented once before in the United States, earlier this year on on Long Island Railroad expansion project in New York City.
Here's how Slowey describes the process:
The developer of the box-jacking system, Italian company Petrucco, is using special hydraulic jacks to push two precast concrete boxes — one 146 feet long and the other 126 feet long and both with 42-foot-long sidewalls — under a roadway east of the airport while an excavator digs out a path from inside the box and from the opposite side. Each box weighs more than 3,000 tons, and the installation will take a 40-person crew working 12-hour shifts around the clock.
Granite Construction, the general contractor for a 37-mile stretch of the Brightline extension, says it will consider using the technique for future projects as well.
FULL STORY: Brightline shaves almost a year from Florida rail project using precast tunnel system

Analysis: Cybertruck Fatality Rate Far Exceeds That of Ford Pinto
The Tesla Cybertruck was recalled seven times last year.

National Parks Layoffs Will Cause Communities to Lose Billions
Thousands of essential park workers were laid off this week, just before the busy spring break season.

Retro-silient?: America’s First “Eco-burb,” The Woodlands Turns 50
A master-planned community north of Houston offers lessons on green infrastructure and resilient design, but falls short of its founder’s lofty affordability and walkability goals.

Test News Post 1
This is a summary

Analysis: Cybertruck Fatality Rate Far Exceeds That of Ford Pinto
The Tesla Cybertruck was recalled seven times last year.

Test News Headline 46
Test for the image on the front page.
Urban Design for Planners 1: Software Tools
This six-course series explores essential urban design concepts using open source software and equips planners with the tools they need to participate fully in the urban design process.
Planning for Universal Design
Learn the tools for implementing Universal Design in planning regulations.
EMC Planning Group, Inc.
Planetizen
Planetizen
Mpact (formerly Rail~Volution)
Great Falls Development Authority, Inc.
HUDs Office of Policy Development and Research
NYU Wagner Graduate School of Public Service