The historic precipitation that fell on the state of California in past months poses a unique and unanticipated threat to the state’s big infrastructure project in the Central Valley.

“Recent rainstorms that have created flooding in some parts of Kings and Tulare counties have also ground work to a halt at several key construction sites for California’s high-speed rail project,” Tim Sheehan for the Fresno Bee. While several work sites are shut down due to the current flooding, officials expect the problem to continue into the summer, as a historic snow pack melts and sends even more water down the state’s various waterways.
Work is continuing along other stretches of the 119-mile stretch of the rail line currently under construction, but on sections impacted by flooding, construction crews have been working to help protect communicates from flooding, according to the article.
Meanwhile, high-speed rail officials report that the project is proving as resilient as it was designed. “The rail line has been designed to cope major floods; viaducts and a railbed that will elevated above the level of the surrounding land are expected to minimize the risk of damage from future floods,” according to the source cited in the article below.
“But it’s the seasonal flow of irrigation ditches and canals that the rail line must cross that represent uncertainty in how fast work can progress this coming fall and winter,” according to Sheehan.
The California High-Speed Rail project has faced numerous challenges through the years, from shifting political winds to cost overruns and planning challenges.
FULL STORY: California’s beleaguered bullet train faces another hurdle: flooding from melting snow

Analysis: Cybertruck Fatality Rate Far Exceeds That of Ford Pinto
The Tesla Cybertruck was recalled seven times last year.

National Parks Layoffs Will Cause Communities to Lose Billions
Thousands of essential park workers were laid off this week, just before the busy spring break season.

Retro-silient?: America’s First “Eco-burb,” The Woodlands Turns 50
A master-planned community north of Houston offers lessons on green infrastructure and resilient design, but falls short of its founder’s lofty affordability and walkability goals.

Test News Post 1
This is a summary

Analysis: Cybertruck Fatality Rate Far Exceeds That of Ford Pinto
The Tesla Cybertruck was recalled seven times last year.

Test News Headline 46
Test for the image on the front page.
Urban Design for Planners 1: Software Tools
This six-course series explores essential urban design concepts using open source software and equips planners with the tools they need to participate fully in the urban design process.
Planning for Universal Design
Learn the tools for implementing Universal Design in planning regulations.
EMC Planning Group, Inc.
Planetizen
Planetizen
Mpact (formerly Rail~Volution)
Great Falls Development Authority, Inc.
HUDs Office of Policy Development and Research
NYU Wagner Graduate School of Public Service