At its Dec. 3 meeting, the CA HSR Authority board members unanimously voted to 'decertify' the program EIR to comply with a judge's order in a suit brought by Peninsula cities and rail and environmental nonprofits over the corridor to the Bay Area.
With the Nov. 3 ruling of Sacramento Superior Court Judge Michael Kenny on the litigation and the Dec. 3 decision of the HSRA made to comply with it now made, there is still uncertainty as to how to how these decisions will affect progress on the project. Altamont Pass (through the East Bay) proponents believe that they now have an opportunity to press their alternative, while HSRA still feel they can go ahead with Pacheco Pass (through the South Bay).
"By a 7-0 vote, the board of the California High Speed Rail Authority on Thursday decertified the massive environmental study that the agency completed last year approving the route. The board directed its staff to draw up new information to add to the study, in particular, various options showing how the trains might go from Gilroy to San Jose if the agency cannot get permission from Union Pacific Railroad to allow high-speed trains to operate in the right of way of existing tracks between the two cities.
Jeff Barker, deputy director of the High Speed Rail Authority, stressed that Thursday's decision does not mean that the agency is abandoning the Pacheco Pass route in favor of a northern route over Altamont Pass, as some groups have urged."
"By no means are we starting from scratch on this," Barker said. "Pacheco Pass is our preferred route."
From SF Chronicle:
"The groups involved in the lawsuit objected to the authority's selection of Pacheco Pass over Altamont Pass as the gateway to the Bay Area, and still consider it a superior choice, said Gary Patton, special counsel for the Planning and Conservation League, which joined in filing the suit.
Peremptory Writ of Mandate (PDF)
Thanks to MTC-ABAG Library
FULL STORY: California high-speed rail route through Pacheco Pass could be adjusted

National Parks Layoffs Will Cause Communities to Lose Billions
Thousands of essential park workers were laid off this week, just before the busy spring break season.

Retro-silient?: America’s First “Eco-burb,” The Woodlands Turns 50
A master-planned community north of Houston offers lessons on green infrastructure and resilient design, but falls short of its founder’s lofty affordability and walkability goals.

Delivering for America Plan Will Downgrade Mail Service in at Least 49.5 Percent of Zip Codes
Republican and Democrat lawmakers criticize the plan for its disproportionate negative impact on rural communities.

Test News Post 1
This is a summary

Test News Headline 46
Test for the image on the front page.

Balancing Bombs and Butterflies: How the National Guard Protects a Rare Species
The National Guard at Fort Indiantown Gap uses GIS technology and land management strategies to balance military training with conservation efforts, ensuring the survival of the rare eastern regal fritillary butterfly.
Urban Design for Planners 1: Software Tools
This six-course series explores essential urban design concepts using open source software and equips planners with the tools they need to participate fully in the urban design process.
Planning for Universal Design
Learn the tools for implementing Universal Design in planning regulations.
EMC Planning Group, Inc.
Planetizen
Planetizen
Mpact (formerly Rail~Volution)
Great Falls Development Authority, Inc.
HUDs Office of Policy Development and Research
NYU Wagner Graduate School of Public Service