Sound Transit had to deliver bad news last week about cost overruns in the design and engineering phase of the East Link rail project that will cross Lake Washington along the path of Interstate 90.
"Before the first tracks [of the East Link] are installed, Sound Transit must spend as much as $20 million in unexpected engineering costs to finish designing the world’s only rail corridor over a floating bridge, as it extends service to the Eastside," reports Mike Lindblom.
Ron Lewis, project director for East Link, "shared the blame between his own team and engineering giant Parsons Brinckerhoff (PB)," according to Lindblom, for "inefficiencies" in the workflow that led to the cost overrun. Parson Brinkerhoff, however, "could now earn $56 million instead of its earlier $36 million contract figure, which began at $28 million in 2012."
So while these design snafus are being ironed out, several major milestones still await the project before construction can begin. Lindblom report, for instance, that "Sound Transit’s final I-90 design, to be approved by the Washington State Department of Transportation (WSDOT), is expected to stretch another year, until late 2016."
The East Link is expected to open in 2023, connecting the International District/Chinatown Station, Bellevue, and Overlake. The funding for the $3.7 billion East Link line was made possible when voters approved a sales-tax increase on a 2008 regional ballot measure.
FULL STORY: Extra $20 million OK’d to finish East Link light-rail design

Analysis: Cybertruck Fatality Rate Far Exceeds That of Ford Pinto
The Tesla Cybertruck was recalled seven times last year.

National Parks Layoffs Will Cause Communities to Lose Billions
Thousands of essential park workers were laid off this week, just before the busy spring break season.

Retro-silient?: America’s First “Eco-burb,” The Woodlands Turns 50
A master-planned community north of Houston offers lessons on green infrastructure and resilient design, but falls short of its founder’s lofty affordability and walkability goals.

Test News Post 1
This is a summary

Analysis: Cybertruck Fatality Rate Far Exceeds That of Ford Pinto
The Tesla Cybertruck was recalled seven times last year.

Test News Headline 46
Test for the image on the front page.
Urban Design for Planners 1: Software Tools
This six-course series explores essential urban design concepts using open source software and equips planners with the tools they need to participate fully in the urban design process.
Planning for Universal Design
Learn the tools for implementing Universal Design in planning regulations.
EMC Planning Group, Inc.
Planetizen
Planetizen
Mpact (formerly Rail~Volution)
Great Falls Development Authority, Inc.
HUDs Office of Policy Development and Research
NYU Wagner Graduate School of Public Service