California's High-Speed Train to Nowhere?

Don't tell that to the 18,000 residents of Shafter. However, the Legislative Analyst's Office made clear in its March 17 report that it questioned having the southern end of the first operating segment located "in an unpopulated agricultural area."

3 minute read

March 21, 2016, 7:00 AM PDT

By Irvin Dawid


FLV California train

California High Speed Rail Authority / Wikimedia Commons

"The nonpartisan office that provides fiscal and policy analysis to the state legislature says it’s concerned about uncertain funding in the California High-Speed Rail Authority’s latest draft business plan and also the proposal to end the initial operating segment (IOS) miles from the nearest urban area in the San Joaquin Valley," writes

[Correspondent's note: A good description of Initial Operating Segments (IOS) can be found in the second paragraph of this Wikipedia description].

The new IOS, referred to as IOS North, resulting from a (literal) change of direction in the draft plan, may be "cheaper and quicker to build," but the southern end in Shafter, 18 miles northwest of Bakersfield in Kern County, creates problems for potential passengers. The Legislative Analyst's report states:

[T]he Legislature will want to consider whether the southern terminus of the proposed IOS makes sense. [U]nder the plan, the IOS North would have its southern terminus at an agricultural area north of the small city of Shafter, which is about 50 miles south of the last planned station on the IOS. In order to make the southernmost portion of the IOS usable, HSRA plans to build a temporary station or platform at this location.

....Even with a temporary station or platform, ending the IOS in an unpopulated agricultural area does not appear to be an effective approach. This is because this location would not have the types of facilities and nearby businesses, such as transit connections, rental car facilities, and shops necessary to meet the needs of train passengers. 

As for the northern end, the high-speed rail train will provide another answer to the question, "Do you know the way to San Jose?" At Diridon Station, passengers can transfer to what will hopefully be an electrified Caltrain for the 47-mile trip to San Francisco. [Currently the diesel-powered trip takes 59 minutes for a 'baby-bullet' or about 90 minutes for a local.]

The other major concern the Legislative Analyst's Office (LAO) expressed was funding—nothing new there as opponents have been pointing this out since the 2008 bond measure authorizing the project was approved by voters. The authority itself recognizes that the train will need to operate before attracting private funds.

However, the Legislative Analyst indicated concerns with the main funding source until the nearly $10 billion in bonds can be tapped.

"[T]he review notes that the possible end of cap-and-trade funding in 2020 'means that without legislative action, the cap-and-trade funds [high-speed rail] plans to use to build the IOS would likely not be available' for the remainder of segment construction, which is expected to be completed in 2025," writes Meacham.

A review of past LAO reports [see two posts in 'related' below 'tags'] on the mega-project show this one could have been a lot worse for the authority.

Expect one more review of the draft business plan to come from a separate Peer Review Group before the draft business plan is sent to the legislature for approval.

For a brief audio account on the LAO's report, click on Capitol Public Radio's report. See Juliet Williams article in The Associated Press (via The Fresno Bee) for a thorough write-up on the report.

Friday, March 18, 2016 in Silicon Valley Business Journal

portrait of professional woman

I love the variety of courses, many practical, and all richly illustrated. They have inspired many ideas that I've applied in practice, and in my own teaching. Mary G., Urban Planner

I love the variety of courses, many practical, and all richly illustrated. They have inspired many ideas that I've applied in practice, and in my own teaching.

Mary G., Urban Planner

Get top-rated, practical training

Red 1972 Ford Pinto with black racing stripes on display with man sitting in driver's seat.

Analysis: Cybertruck Fatality Rate Far Exceeds That of Ford Pinto

The Tesla Cybertruck was recalled seven times last year.

July 2, 2025 - Mother Jones

Close-up of park ranger in green jacket and khaki hat looking out at Bryce Canyon National Park red rock formations.

National Parks Layoffs Will Cause Communities to Lose Billions

Thousands of essential park workers were laid off this week, just before the busy spring break season.

February 18, 2025 - National Parks Traveler

Paved walking path next to canal in The Woodlands, Texas with office buildings in background.

Retro-silient?: America’s First “Eco-burb,” The Woodlands Turns 50

A master-planned community north of Houston offers lessons on green infrastructure and resilient design, but falls short of its founder’s lofty affordability and walkability goals.

February 19, 2025 - Greg Flisram

Screenshot of shade map of Buffalo, New York with legend.

Test News Post 1

This is a summary

0 seconds ago - 2TheAdvocate.com

Red 1972 Ford Pinto with black racing stripes on display with man sitting in driver's seat.

Analysis: Cybertruck Fatality Rate Far Exceeds That of Ford Pinto

The Tesla Cybertruck was recalled seven times last year.

18 minutes ago - Mother Jones

test alt text

Test News Headline 46

Test for the image on the front page.

March 5 - Cleantech blog