The SafeTrack repair program has shut down Metrorail lines for much of 2016—and the price for the repairs to the system keep going up.

"Metro’s SafeTrack maintenance program will cost significantly more than anticipated and take at least three months longer to complete," reports Martine Powers, based on the information provided in a progress report released last week.
"The report by the Federal Transit Administration estimates that the total cost of the project will be $118.8 million — nearly twice the $60 million price tag Metro General Manager Paul J. Wiedefeld floated in June," adds Powers.
The article goes into detail about where the WMATA's cost estimates and the cost estimates of the Federal Transit Administration differ. Then there is this other detail that will disappoint, but probably not surprise, transit users in the Washington, D.C. region: the progress report estimates that the program will end in June, rather than the originally estimated March completion date.
FULL STORY: Metro’s SafeTrack could cost twice as much as expected and likely won’t conclude until June

Analysis: Cybertruck Fatality Rate Far Exceeds That of Ford Pinto
The Tesla Cybertruck was recalled seven times last year.

National Parks Layoffs Will Cause Communities to Lose Billions
Thousands of essential park workers were laid off this week, just before the busy spring break season.

Retro-silient?: America’s First “Eco-burb,” The Woodlands Turns 50
A master-planned community north of Houston offers lessons on green infrastructure and resilient design, but falls short of its founder’s lofty affordability and walkability goals.

Test News Post 1
This is a summary

Analysis: Cybertruck Fatality Rate Far Exceeds That of Ford Pinto
The Tesla Cybertruck was recalled seven times last year.

Test News Headline 46
Test for the image on the front page.
Urban Design for Planners 1: Software Tools
This six-course series explores essential urban design concepts using open source software and equips planners with the tools they need to participate fully in the urban design process.
Planning for Universal Design
Learn the tools for implementing Universal Design in planning regulations.
EMC Planning Group, Inc.
Planetizen
Planetizen
Mpact (formerly Rail~Volution)
Great Falls Development Authority, Inc.
HUDs Office of Policy Development and Research
NYU Wagner Graduate School of Public Service