The New York Times has a potential damning report about shortcuts taken by the New York MTA, under the leadership of Governor Andrew Cuomo, to deliver the Second Avenue Subway on its scheduled opening date at the beginning of the year.

"In a rush to finish New York City’s long-awaited Second Avenue subway by a New Year’s Day deadline imposed by Gov. Andrew M. Cuomo, the Metropolitan Transportation Authority failed to complete final safety testing before opening the line to the public," reports Emma G. Fitzsimmons.
Fire systems were still being tested when the new subway opened on January 1, adds Fitzsimmons. "Now more than eight months after the lavish opening, complete with sparkling wine and an elegant midnight celebration on New Year’s Eve, the subway line is still operating under a temporary safety certificate, according to the Federal Transit Administration." Another detail of the ongoing status of safety systems on the city's newest subway: "Crews have had to be posted along the line to watch for fires — an expensive effort meant to serve as a stopgap."
Fitzsimmons discovered the status of safety on the new subway line through a Freedom of Information request for reports prepared by Urban Engineers of New York for the Federal Transit Administration.
The article includes a quote by John McCarthy, a spokesperson for the Metropolitan Transportation Authority, defending the safety precautions in place on the new subway line. MTA Chair Joseph J. Lhota also states that the subway line was not opened prematurely. Still, thousands of defects were still waiting to be fixed in May, and there is not shortage of sources willing to say that the opening circumvented safety protocols.
The article is allowed a word count commensurate with the seriousness of the accusations made by the reports, so there is a lot more detail included in the source article.
FULL STORY: Months After Second Avenue Subway Opening, Safety Testing Is Not Finished

Analysis: Cybertruck Fatality Rate Far Exceeds That of Ford Pinto
The Tesla Cybertruck was recalled seven times last year.

National Parks Layoffs Will Cause Communities to Lose Billions
Thousands of essential park workers were laid off this week, just before the busy spring break season.

Retro-silient?: America’s First “Eco-burb,” The Woodlands Turns 50
A master-planned community north of Houston offers lessons on green infrastructure and resilient design, but falls short of its founder’s lofty affordability and walkability goals.

Test News Post 1
This is a summary

Analysis: Cybertruck Fatality Rate Far Exceeds That of Ford Pinto
The Tesla Cybertruck was recalled seven times last year.

Test News Headline 46
Test for the image on the front page.
Urban Design for Planners 1: Software Tools
This six-course series explores essential urban design concepts using open source software and equips planners with the tools they need to participate fully in the urban design process.
Planning for Universal Design
Learn the tools for implementing Universal Design in planning regulations.
EMC Planning Group, Inc.
Planetizen
Planetizen
Mpact (formerly Rail~Volution)
Great Falls Development Authority, Inc.
HUDs Office of Policy Development and Research
NYU Wagner Graduate School of Public Service