The news keeps getting worse at San Francisco's newly opened, since closed, Salesforce Transit Center.

After barely more than a month of operation, the $2.2 billion Salesforce Transit Center was closed in September after inspectors discovered cracks in two of the building's four steel support beams.
Since then, the legal and political drama has taken hold.
"San Francisco city officials are withholding $9.6 million meant to fund expansion planning for the Salesforce Transit Center, in a bid to hold its leadership accountable for alleged mismanagement of the $2.2 billion project," reported Joe Fitzgerald Rodriguez on October 18.
"That funding was aimed toward design and engineering of a planned future phase of the transit center, in which the basement floor will be converted to accommodate California High Speed Rail and a soon-to-be electrified Caltrain," adds Fitzgerald Rodriguez. (There's more on the threat to future planning efforts later in this article).
News of the city's reluctance to continue funding the project came a day after news of a lawsuit, reported by Rachel Swan, over mismanagement of the project. That lawsuit doesn't even mention the cracked beams. Swan explains:
The suit covers the $2.2 billion center’s construction phase and makes no mention of the current problems facing the facility....But the action is the latest in a series of lawsuits stemming from the project’s delays and cost overruns, and it blames the authority for “mismanagement, failures, and delays.”
Fast forward to this week, when the San Francisco County Transportation Authority Board voted to finalize the decision to suspend funding for next planning steps for the project "until The City can evaluate what led to the discovery last month of cracks in two steel beams, shutting down the newly constructed $2.2 billion transit center," according to the most recent article on the subject from Fitzgerald Rodriguez.
From another article by Rachel Swan comes more bad news that testing of the cracked steel beams has been delayed—results are now expected back in mid-November. "Only then can officials determine what happened and how to fix it, said Mark Zabaneh, executive director of the Joint Powers Authority, speaking to the authority Tuesday. A reopening date has not been set," according to Swan.
FULL STORY: City withholds Salesforce Transit Center funding as allegations of mismanagement mount

Analysis: Cybertruck Fatality Rate Far Exceeds That of Ford Pinto
The Tesla Cybertruck was recalled seven times last year.

National Parks Layoffs Will Cause Communities to Lose Billions
Thousands of essential park workers were laid off this week, just before the busy spring break season.

Retro-silient?: America’s First “Eco-burb,” The Woodlands Turns 50
A master-planned community north of Houston offers lessons on green infrastructure and resilient design, but falls short of its founder’s lofty affordability and walkability goals.

Test News Post 1
This is a summary

Analysis: Cybertruck Fatality Rate Far Exceeds That of Ford Pinto
The Tesla Cybertruck was recalled seven times last year.

Test News Headline 46
Test for the image on the front page.
Urban Design for Planners 1: Software Tools
This six-course series explores essential urban design concepts using open source software and equips planners with the tools they need to participate fully in the urban design process.
Planning for Universal Design
Learn the tools for implementing Universal Design in planning regulations.
EMC Planning Group, Inc.
Planetizen
Planetizen
Mpact (formerly Rail~Volution)
Great Falls Development Authority, Inc.
HUDs Office of Policy Development and Research
NYU Wagner Graduate School of Public Service