Instagram images and group bike rides now celebrate the Bay Bridge’s eastern span, but the bridge’s long construction process was a constant source of concern. A new report details what went wrong to (hopefully) prevent future mistakes.
A new report titled “The San Francisco Oakland Bay Bridge: Basic Reforms for the Future” produces a scathing account of the many scofflaws of the construction of the new eastern span of the Bay Bridge. The most concerning finding of the report, “an institutionalized, if not malicious, lack of transparency,” on the part of state transportation agency Caltrans.
Lee Romney writes that Caltrans isn’t the only guilt party according to the report’s account of the cost overruns, delays, and falsified reports that plagued the project. “The report spreads blame for delays among the U.S, Navy, the cities of Oakland and San Francisco, environmental groups, the Metropolitan Transportation Commission, the state Legislature and ‘actions taken at the very highest levels of the state’s executive branch [that] also cost — rather than saved — time and money.’”
Romney notes, however, that “the harshest criticism is reserved for the way Caltrans treated those who raised concerns. Among them: One respected outside engineer was told he was being ‘too rigorous’ in expressing concerns about widespread cracks in Chinese-made welds, an interview revealed. He also raised questions about the anchor rods and was told 'basically to stop bringing it up.'"
FULL STORY: Bay Bridge safety critics were told to keep quiet, report finds

Analysis: Cybertruck Fatality Rate Far Exceeds That of Ford Pinto
The Tesla Cybertruck was recalled seven times last year.

National Parks Layoffs Will Cause Communities to Lose Billions
Thousands of essential park workers were laid off this week, just before the busy spring break season.

Retro-silient?: America’s First “Eco-burb,” The Woodlands Turns 50
A master-planned community north of Houston offers lessons on green infrastructure and resilient design, but falls short of its founder’s lofty affordability and walkability goals.

Test News Post 1
This is a summary

Analysis: Cybertruck Fatality Rate Far Exceeds That of Ford Pinto
The Tesla Cybertruck was recalled seven times last year.

Test News Headline 46
Test for the image on the front page.
Urban Design for Planners 1: Software Tools
This six-course series explores essential urban design concepts using open source software and equips planners with the tools they need to participate fully in the urban design process.
Planning for Universal Design
Learn the tools for implementing Universal Design in planning regulations.
EMC Planning Group, Inc.
Planetizen
Planetizen
Mpact (formerly Rail~Volution)
Great Falls Development Authority, Inc.
HUDs Office of Policy Development and Research
NYU Wagner Graduate School of Public Service